Pembangunan Rumah Pompa Bulak Cabe Capai 60 Persen

Bulak Cabe Pump House Construction Reaches 60 Percent

Each pump will have between 500-3,500 liters per second capacity

The Bulak Cabe pump house construction in Cilincing Urban Village, North Jakarta that has been executed since June has reached 60 percent.

Pump Houses and Sluice Gates in Taman Sari Ensured to Be in Good Condition

North Jakarta Water Resources (SDA) Agency Head Adrian Maulana said, the physical construction includes pumping stations, stationary pumps and sheetpiles for processed ponds.

"Each pump will have between 500-3,500 liters per second capacity," he expressed, Monday (11/18).

Thus far the construction of the sheet pile up to one kilometer and pump house has been completed.

"And now we are preparing mechanical and electrical stages. They will be connected with stationary pump installations and trials," he told.

It is expected to be able to minimize flooding due to overflowing waters of the Cakung Lama and Gubug Genteng rivers in Sukapura, Pegangsaan Dua, Semper Barat, Tugu Selatan and Semper Timur urban villages.

"It is targeted to be complete in December and to operate in 2020," he stressed.

Linked News
Popular News indeks
  1. Transjabodetabek PIK 2-Blok M Route Serves 1.4 Million Passengers

    access_time24-05-2026 remove_red_eye1841 personAldi Geri Lumban Tobing
  2. Kultura Market in Pademangan Barat Attracts Crowds

    access_time22-05-2026 remove_red_eye1124 personAnita Karyati
  3. West Jakarta to Host Career Day Walk-in Interviews Next Week

    access_time21-05-2026 remove_red_eye1124 personBudhi Firmansyah Surapati
  4. Jakarta Government Hosts Jakarta Sales Mission in China

    access_time25-05-2026 remove_red_eye693 personAldi Geri Lumban Tobing
  5. Commission E Pushes for Evaluation of Free Private School Program

    access_time25-05-2026 remove_red_eye681 personFakhrizal Fakhri